The Palace court Addition


updated : March 12, 2008 8:36 AM

Well, We decided to add an addition to the Palace ct house. This house is my 6th "fixer-upper"...But this is clearly my most ambitious project to date ! We have hired out the foundation turnkey, from there its going to be pretty much just us workers ! We'll have to see how this goes !!
Pre-Project Projects
__
we dropped about 6 trees for this, resulting in about 4 cords of campfire wood !! (note Axe head vs. Alec's eye's !!)
Before : front
Before : rear


Foundation (1st Choice Concrete) Ground break 3/8/2006
To achieve the 8ft ceiling height we had to undermine the existing footing.
This resulted in a HUGE support wall
Backfilled and completed 3/28/06, Excellent job, graded yard, square/level with .25inch !!

Framing begins; Set/Level sill plates on 4/2/06, closed in 6/16/06 (4 weeks lost to incompetent hired help)

Windows and siding (siding 12/12/06) and future deck

Inside happenings

Basement, deck and patio

Siding Project

Miscellaneous and general